Projects
Projects
Construction and securing of downstream flood drainage system, access road, and remaining works of Narmashir (Nesa) dam
Start date:
12-August-2020
Due date:
21-June-2023
Status:
Completed
Technical area:
Water And Environment - Flood Protection System
Employer:
Regional water company of Kerman
Background:
Following the occurrence of a great flood in 2017 at the site of the Narmashir Dam, the flood drainage system of the Nesa Dam started to discharge. This flood caused severe erosion of the downstream waterway and destroyed three dikes and a village 4 kilometers away from the dam. Therefore, Tunnel Sadd Ariana Company, based on its social duty, decided to repair and renovate the place.
Roles:
- Construction of access roads
- Execution of the structure of the spillway canal of Nesa’s Dam with 511 meters length
- Equipping and repairing dam’s office buildings
- Implementation of the water supply system to the official site
- Execution of greenbelt from the dam’s spillway